By status
Mothballed LNG infrastructure
4 LNG terminals in 3 countries totalling 30.8 Mtpa and 8 gas pipelines totalling 6,768 km are mothballed. Terminals are sorted by capacity, pipelines by length, vessels by cargo capacity.
4 mothballed LNG terminals
| Import / export | Type | Units | |||||
|---|---|---|---|---|---|---|---|
| Lake Charles LNG TerminalLouisiana | United States | Import | Not reported | Mothballed | 17.9 Mtpa | 2 | 1982 |
| Yemen LNG TerminalShabwah | Yemen | Export | Not reported | Mothballed | 6.7 Mtpa | 2 | 2009 |
| Marsa El Brega LNG TerminalCyrenaica | Libya | Export | Not reported | Mothballed | 3.2 Mtpa | 4 | 1970 |
| Neptune LNG TerminalMassachusetts | United States | Import | Not reported | Mothballed | 3.04 Mtpa | 1 | 2010 |
8 mothballed gas pipelines
| Countries | Segments | |||||
|---|---|---|---|---|---|---|
| Soyuz Gas PipelineOrenburg → Uzhgorod | Russia, Ukraine, Kazakhstan | Mothballed | 2,750 km | 25.2 bcm/y | 1 | 1980 |
| Nord Stream 2 Gas PipelineUst Luga → Greifswald | Russia, Finland, Sweden, Denmark, Germany | Mothballed | 1,230 km | 55 bcm/y | 1 | 2022 |
| Nord Stream Gas PipelineVyborg → Greifswald | Russia, Germany | Mothballed | 1,222 km | 55 bcm/y | 1 | 2011 |
| Russian Federation – Turkey Natural Gas Main Transmission LineMalkoclar → Ankara | Russia, Türkiye | Mothballed | 842 km | 4 bcm/y | 1 | 1986 |
| Ostrogozhsk-Shebelinka Gas PipelineOstrogozhsk → Shebelinka | Ukraine, Russia | Mothballed | 312 km | 22.5 bcm/y | 1 | 1981 |
| Trans-Caribbean Gas PipelineBallena gas fields → Maracaibo | Venezuela, Colombia | Mothballed | 224 km | 5 bcm/y | 1 | 2007 |
| Arab Gas PipelineHoms → Deir Ammar | Syria, Lebanon | Mothballed | 101 km | 10.3 bcm/y | 1 | 2009 |
| Tubridgi Pipeline SystemTalandji → Nanutarra | Australia | Mothballed | 87 km | 0.3 bcm/y | 1 | 1991 |