Tegalgede-Muara Tawar Gas Pipeline is a cancelled gas transmission pipeline in Indonesia. The tracker lists 1 tracked segment, 50 km long, starting up in 2021. It runs from Tegalgede to Muara Tawar.

Length

50 km

Capacity

Not reported

Segments tracked

1

Route

Tegalgede-Muara Tawar Gas Pipeline runs from Tegalgede to Muara Tawar. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Tegalgede
To
Muara Tawar
Start country
Indonesia
End country
Indonesia
Countries crossed
Indonesia
Onshore / offshore
Not reported
Fuel
Gas
Region
Asia
Route drawn on map
35 km
GEM pipeline ID
P0985
Start year
2021
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineCancelledTegalgede → Muara Tawar50Not reported2021GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Nusantara Regas Satu TerminalIndonesiaImportOperating22.7 kmroute proximity

Owners and operators

Stakes as reported by GEM per segment, merged across segments.