LNG Chain

Gas transmission pipeline · Rihab to Jaber (Jordanian-Syrian Border)

Arab Gas Pipeline

Arab Gas Pipeline is an operating gas transmission pipeline in Jordan. The tracker lists 1 tracked segment, 30 km long and 10.3 bcm/y of capacity, starting up in 2007. It runs from Rihab to Jaber (Jordanian-Syrian Border). It is owned by Jordanian Egyptian Fajr Natural Gas Co.

Length

30 km

Capacity

10.3 bcm/y

7.6 Mtpa LNG equivalent

Segments tracked

1

Largest diameter 914 mm (36 in)

Route

Arab Gas Pipeline runs from Rihab to Jaber (Jordanian-Syrian Border). The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Rihab
To
Jaber (Jordanian-Syrian Border)
Start country
Jordan
End country
Jordan
Countries crossed
Jordan
Onshore / offshore
Not reported
Fuel
Gas
Region
Asia
Route drawn on map
23 km
GEM pipeline ID
P7539
Start year
2007
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Rihab-Jaber Gas PipelineOperatingRihab → Jaber (Jordanian-Syrian Border)3010.3914 mm2007GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

No tracked LNG terminal lies within 25 km of this pipeline's route.

Owners and operators

Stakes as reported by GEM per segment, merged across segments.