Country
Tanzania: LNG infrastructure
Tanzania has 1 LNG terminal and 4 tracked gas pipelines in the Global Energy Monitor tracker. It operates no LNG terminal capacity, and none is under construction.
Export capacity
—
operating liquefaction
Import capacity
—
no import terminal tracked
Pipelines
4
2,635 km tracked
Fleet
0
0 flagged, 0 owned from here
Import and export balance
| Direction | Terminals | Operating | Under construction |
|---|---|---|---|
| Export (liquefaction) | 1 | — | — |
| Import (regasification) | 0 | — | — |
Figures are whole-terminal capacities in Mtpa, not adjusted for ownership stakes or utilisation.
LNG terminals in Tanzania
| Import / export | Type | Units | ||||
|---|---|---|---|---|---|---|
| Tanzania LNG TerminalLindi | Export | Not reported | Proposed | 10 Mtpaproposed | 2 | — |
Gas pipelines crossing Tanzania
Any pipeline whose country list includes this country, including transit pipelines that only pass through.
| Countries | Segments | |||||
|---|---|---|---|---|---|---|
| Mtwara–Dar es Salaam Gas PipelineMadimba Village → Dar es Salaam | Tanzania | Operating | 535 km | 8.1 bcm/y | 1 | 2015 |
| Songas PipelineSongo Songo Island → Dar es Salaam | Tanzania | Operating | 225 km | 1.07 bcm/y | 1 | 2004 |
| Tanzania–Kenya Gas PipelineDar es Salaam → Mombasa | Tanzania, Kenya | Proposed | 600 km | Not reported | 1 | — |
| Uganda Tanzania Pipeline | Uganda, Tanzania | Shelved | 1,275 km | Not reported | 1 | 2021 |
Chokepoint exposure
Chokepoint exposure is shown on each terminal page, taken from a hand-maintained trade-lane table. It is an editorial routing model of typical laden voyages, not vessel tracking. The exposure feed aggregates it by chokepoint.