Gas transmission pipeline · Baghdad to Dora
Taji-Duara Gas Pipeline
Taji-Duara Gas Pipeline is an operating gas transmission pipeline in Iraq. The tracker lists 1 tracked segment, 32 km long by route geometry and 0.96 bcm/y of capacity. It runs from Baghdad to Dora. It is owned by Iraq Ministry of Oil.
Length
32 km
Measured from the route geometry; GEM does not report a length.
Capacity
0.96 bcm/y
0.7 Mtpa LNG equivalent
Segments tracked
1
Largest diameter 457 mm (18 in)
Route
Taji-Duara Gas Pipeline runs from Baghdad to Dora. The map draws the tracked route and any LNG terminal within 25 km of it.
Loads about 250 kB of map code and the country outline file.
- From
- Baghdad
- To
- Dora
- Start country
- Iraq
- End country
- Iraq
- Countries crossed
- Iraq
- Onshore / offshore
- Not reported
- Fuel
- Gas
- Region
- Asia
- Route drawn on map
- 32 km
- GEM pipeline ID
- P4054
- Start year
- Not reported
- GEM wiki page
- gem.wiki
Segments
Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.
| Segment | Status | From → to | Length | Capacity | Diameter | Start | Route from |
|---|---|---|---|---|---|---|---|
| Whole pipeline | Operating | Baghdad → Dora | 32 | 0.96 | 457 mm | — | GEM's route file |
Connected LNG terminals
Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.
No tracked LNG terminal lies within 25 km of this pipeline's route.
Owners and operators
Stakes as reported by GEM per segment, merged across segments.