LNG Chain

Gas transmission pipeline · Vilnius to Riga

Lithuania-Latvia Interconnection Gas Pipeline

Lithuania-Latvia Interconnection Gas Pipeline is an operating gas transmission pipeline crossing Lithuania, Latvia. The tracker lists 1 tracked segment, 138 km long and 2.3 bcm/y of capacity, starting up in 1962. It runs from Vilnius to Riga. It is owned by Latvijas Gaze and Energijos Skirstymo Operatorius.

Length

138 km

Capacity

2.3 bcm/y

1.7 Mtpa LNG equivalent

Segments tracked

1

Route

Lithuania-Latvia Interconnection Gas Pipeline runs from Vilnius to Riga. The map draws the tracked route and any LNG terminal within 25 km of it.

Loads about 250 kB of map code and the country outline file.

From
Vilnius
To
Riga
Start country
Lithuania
End country
Latvia
Countries crossed
Lithuania, Latvia
Onshore / offshore
Not reported
Fuel
Gas
Region
Europe
Route drawn on map
101 km
GEM pipeline ID
P0705
Start year
1962
GEM wiki page
gem.wiki

Segments

Each row is one row of GEM's pipeline file. Project-level figures repeated on every segment are counted once in the totals above.

SegmentStatusFrom → toLengthCapacityDiameterStartRoute from
Whole pipelineOperatingVilnius → Riga1382.31962GEM's route file

Connected LNG terminals

Terminals whose coordinates fall within 25 km of this route, or whose name matches the pipeline. Proximity is not proof of a physical connection.

TerminalCountryImport / exportStatusDistanceMatched by
Riga FSRULatviaImportCancelled5.1 kmroute proximity

Owners and operators