What terminal status actually means

A project status describes how far an LNG terminal or train has progressed, and the gap between proposed and operating is the single most misread number in the industry.

The nine states

This site maps every project onto one nine-value scale, so a terminal, a pipeline and a vessel can be compared on the same terms.

Proposed. Announced or in permitting, with no final investment decision. The widest and least reliable category.

Pre-construction. Committed, usually past a final investment decision or holding its permits, but no ground broken.

Construction. Being built. For an LNG train this means several years of work, module fabrication and commissioning ahead.

Operating. Producing or receiving cargoes commercially.

Idle. Built and capable, but not currently working. A market condition rather than a technical one.

Mothballed. Taken out of service deliberately and preserved so it could restart.

Shelved. A development paused indefinitely. Not built, not formally dead.

Cancelled. Abandoned before completion.

Retired. Permanently closed or dismantled.

Why the proposed number misleads

The most common error in LNG analysis is adding proposed capacity to operating capacity and presenting the total as what the world will have.

Proposed capacity has always exceeded what gets built, often by a wide margin. Projects are announced to test the market, secure acreage, attract partners or influence policy, and many never intend to reach construction. Others are real but lose their race for offtake contracts, because a buyer signs with a competitor and the project quietly stops.

The discipline is simple: never add across statuses without saying which ones. On every page here, operating, under construction and proposed capacities sit in separate columns and are never summed into a single headline. When a terminal shows nothing operating and a figure under construction, the summary sentence says exactly that rather than implying the site is dark.

Reading a multi-train terminal

A large export terminal is rarely in one state. It may have three trains operating, one commissioning, and three more approved but unbuilt. Describing it with one word loses precisely the information that matters.

Our approach is a rolled-up status plus the detail beneath it. The roll-up takes the most advanced state present, so a site with anything operating reads as operating. Below it, every train appears with its own status, capacity and start year. The capacity cards separate the three states so the shape of the project is visible at a glance.

The same logic applies to a country page. A country with nothing operating and a large project under construction is in a different position from one with neither, and the numbers should show that difference rather than hiding it behind a zero.

Where statuses come from and where they go wrong

We do not assign statuses ourselves. We map the tracker’s own wording onto the nine values above, case-insensitively, handling the qualifiers that appear in real data. Text we cannot map is preserved and displayed verbatim on the asset page, and the unit is shown as “Not reported” rather than being guessed into a bucket.

Two caveats are worth carrying. Status is a snapshot at a release date, and a tracker published annually will lag reality by up to a year for fast-moving projects; every page states the release it came from. And status is a judgement made by the data’s compilers, particularly for the boundary between shelved, cancelled and merely quiet.

You can browse everything by status, and each status page lists the terminals, pipelines and vessels in that state, sorted by size.

Common questions

Each answer stands on its own.

What does pre-construction mean for an LNG project?
That the project has cleared its main hurdles, usually a final investment decision or its permits, but has not started building. It is the strongest signal short of construction that capacity is genuinely coming.
Is proposed capacity likely to be built?
Historically much of it is not. Proposed covers everything from a press release to an advanced permit application, and a large share never reaches a final investment decision.
What is a final investment decision?
The point at which the owners commit the money and sign the construction contracts. Before it, a project is an intention; after it, a commitment with contracts behind it.
What is the difference between mothballed and shelved?
Mothballed describes a built facility taken out of service but maintained so it could restart. Shelved describes a project that was never built and whose development has been paused indefinitely.
Why do capacity figures differ between sources?
Mostly because of which statuses they include. A figure counting proposed projects can be several times one counting only operating capacity, and headlines rarely say which is which.