Nicaragua: LNG infrastructure
Nicaragua has 1 LNG terminal in the Global Energy Monitor tracker. Nothing is operating yet, but 5 Mtpa is under construction, all of it regasification for import.
Export capacity
—
no export terminal tracked
Import capacity
—
5 Mtpa under construction
Pipelines
0
crossing this country
Fleet
0
0 flagged, 0 owned from here
Import and export balance
| Direction | Terminals | Operating | Under construction |
|---|---|---|---|
| Export (liquefaction) | 0 | — | — |
| Import (regasification) | 1 | — | 5 |
Figures are whole-terminal capacities in Mtpa, not adjusted for ownership stakes or utilisation.
LNG terminals in Nicaragua
| Import / export | Type | Units | ||||
|---|---|---|---|---|---|---|
| Puerto Sandino FSRU | Import | FSRU | Under construction | 5 Mtpaunder construction | 1 | — |